Cavarosa's construction progresses with key milestones in structural foundation and water infrastructure, setting the stage for a resilient seaside development.

Every phase of Cavarosa reflects our commitment to thoughtful planning, structural excellence, and lasting quality, creating a development designed to stand the test of time by the sea.
Roy Mendieta, Project Manager at MARAZUL, shares the latest construction milestones and what's ahead as the project enters the new year.
1. Structural Foundation Caps
2. Slab at Level -350
3. Water Storage Tank
Structural work: 12% complete.
Water storage tank: 61% complete.
Foundations (Slabs at levels -350 and -300): 17% complete.
January marks the official start of a major new phase: concrete structural construction.
As the project moves beyond site preparation, Cavarosa is steadily taking shape, supported by a solid and carefully engineered foundation.
Every completed phase brings the development closer to its next milestone, reflecting a disciplined construction process guided by strict technical and quality standards.
We continue to build with vision, precision, and a commitment to responsible planning.
Estimated delivery: Starting in the first quarter of 2028.