Cavarosa continues to take shape

See Cavarosa’s October construction progress in Amador: structural work is 61% complete, with construction completion estimated for Q1 2028.

AVANCES CAVAROSA BANNER BLOG

 

Cavarosa, TheVelopers’ residential development in Amador, Panama, reports 61% completion of the tower’s structural work in its October update. Construction continues with concrete work, interior spaces, and building systems. Construction completion is estimated for the first quarter of 2028.

 

Each new stage brings Cavarosa’s architecture further to life. As the tower continues to rise, work on the lower levels is shaping the spaces and systems that will support the building’s future use.

 

Here is a closer look at October’s key construction updates and the next milestones for this stage of the project.

 

 

Key construction progress at Cavarosa in October 2026

 

  • Tower structure: The October update reports 61% completion of the tower’s structural work. Vertical construction continues alongside interior work on the lower levels.


  • Concrete slabs and structural work: During the month, the scheduled concrete pours at levels 600, 1200, and 1300 were completed. Additional structural work was carried out between levels 1100 and 1200.

    These activities are part of the ongoing construction of the structure that defines the tower’s different levels.


  • Interior spaces: Work on the lower levels progressed with the construction of masonry block walls, the installation of railings, and work in the bathrooms.

    These activities are gradually defining the interior layout as construction continues on the levels above.


  • Electrical and plumbing installations: Electrical and plumbing work continues in coordination with structural construction. These installations form part of the systems needed for the building’s future operation.



 

What are Cavarosa’s next construction milestones?

 

The next stage of work focuses on three areas:

 

  1. Continued structural construction: Concrete pours are planned to continue at levels 700, 1300, and 1400, allowing the tower to keep rising.

  2. Development of the lower levels: Planned activities include ramp construction, work on stairways, and other work needed to connect and prepare different areas of the building for use.

  3. Building systems and interior spaces: Electrical, sanitary, and plumbing work will continue, alongside planning for air conditioning systems, swimming pools, and building enclosures.

 

 

Press play to learn more.

 

What does this progress mean for the project?

 

Cavarosa has reached a stage where vertical construction and interior development are moving forward in parallel. As the structure rises, the lower levels are incorporating the elements that will define the building’s layout, functionality, and operation.

 

For future owners, this update provides a clear view of the work completed and the activities planned for the next stage. Each milestone brings Cavarosa closer to realization, supported by the technical oversight that accompanies its construction.

 

 

Ver galería completa

 

 

A vision by TheVelopers.

 


 

Completion estimated for Q1 2028.

 